|
Today's Feature
Memorial Hall
Renovation Chronology.
The following is a memo
issued by City Administrator Tom Short to the
City Council concerning the history of the
Memorial Hall renovation project.
"Due to the length of this
project and changes in the composition of the
various Council Committees and the City Council,
included is a short chronology of events and
actions regarding the renovation work for the
Memorial hall.
In January 1998, the City
established the Memorial Hall Long-Range Planning
Committee. The City Council requested the
Committee recommend a master facility plan for
the Memorial Hall Building that would define its
best current and potential usages meeting the
entertainment, cultural, recreational, economic
and other appropriate needs of the community. The
Committee submitted its report in May 1998, to
the Council. As part of their recommendations,
the Committee recommended the services of an
architect to develop recommended improvements. In
September of 1998, the Architectural firm of
Pellham, Phillips, Hagerman was hired by the City
to provide a long-range development plan for the
Hall. This plan was received by the City in
February 1999. Due to the magnitude of required
funding for the plan and the Citys lack of
funds, no work on the plan was begun. In March
and April of 1999, grant requests were sent to
local foundations for more than $1.6 to
accomplish the project. Additionally, late in the
fall of 1998 staff became aware of the Missouri
Veterans Commission grant funds available for
veteran memorials. An application deadline for
these projects was after July 1999. In March
2000, the Public Services Committee, in light of
the Veterans Grant, developed a scope of work
that could be funded by the grant pursuant to
their guidelines. In April 2000, the Memorial
Hall Long-Range Planning Committee was asked to
re-evaluate the Master Plan that had been
submitted to the Council due to changes since the
plan was submitted. The Committee also reviewed
the grant application to Veterans Commission. The
Committee supported the application as ultimately
approved by the Council. In November 2000, the
City signed a contract with Pellham, Phillips,
Hagerman for services to prepare plans and
specifications of the project. The Public
Services Committee was intimately involved in the
review and approval of the specs and the City
authorized the architects to solicit bids. The
City was notified August 2000, of approval of the
first Veterans grant. In April 2001,
requests for bids were sent out to known
contractors of the construction for the
improvements. On June 1, 2001, bids were opened
in an amount substantially higher than
anticipated. Since that time a second application
was sent to the Veterans Commission for a portion
of the additional funding for the project. An
application was authorized by the City June 2001,
for the additional amount. In September 2001, the
City submitted an amended application to the
Boylan foundations for $100,000 and the Steadley
Foundation for $250,000. The Steadley Foundation
agreed to match any award the Boylan Foundation
granted to the City up to $100,000. The Boylan
Foundation did not approve the request by the
City. In September 2001, the City received notice
from the Commission of approval for the
additional funds . Following is a breakdown of
some of the specific items that transpired after
the bids opening.
At the September 13, 2001,
Council meeting, the Council voted to accept the
recommendation of the Public Services Committee
to accept the bid of R.E. Smith Construction Co.
in the amount of $1,071,000. It was reported by
the Committee Chairman that the amount exceeded
budget but this would enable the City to proceed
with negotiations with the contractor. He also
noted that the City had only appropriated
$800,000 for this project so cuts would be
necessary.
At the Public Services
Committee meeting of September 20, 2001, it was
reported staff, Joe Jensen (Pellham, Phillips
& Hagerman) and Jason Eckhart (Sprenkle &
Asso.) had met with Dave Smith of R.E. Smith
Construction Co. to discuss the scope of work for
the project. The contractor presented an itemized
list of bid items. These, however, were not in a
format comparable to the Architects
estimates on a floor by floor basis. The
Committee discussed prioritizing the components
of the project. After discussion it was agreed
that the elevator was first, the roof second, the
veterans offices third, the entrance and
museum fourth and the basement last. Therefore,
in order for the project to come within budget,
the contractor would come back with his numbers
deleting the basement work, except for the HVAC
system and the kitchen appliances, from the
project. As the roof installation was weather
dependent, the contractor wished to begin this
portion as soon as possible. Therefore, staff
would work to have a proposed contract for the
October 9, 2001, Council meeting for adoption as
an emergency. The Committee also discussed the
possibility, if needed, of requesting an
appropriation of additional funds depending on
negotiations with the contractor.
At the Public Services
Committee meeting of October 1, 2001, the
Committee received a revised price on the project
from R.E. Smith in the amount of $862,000 with
the deletion of the basement work. The Committee
also discussed the possibility of completing the
original scope of work and a potential budget
adjustment to accomplish it. After discussion,
the Committee voted to recommend the entire
project to the Council.
The Budget Committee, at their
October 8, 2001 meeting, also discussed the
Memorial Hall project in conjunction with the
discussion and recommendation made by the Public
Services committee. The Budget Committee reviewed
information as to how the City could reallocate
current budget items to provide adequate funds to
cover the entire contemplated cost of the
project. After discussion, the Committee voted
three to one to recommend doing the entire scope
of work as originally contemplated to the full
Council and making the appropriate budge
adjustments at the next Council meeting.
At the Council meeting of
October 9, 2001, the Council, after discussion,
voted (6-4) to accept the recommendations of the
Public Services Committee and the Budget Ways
& Means Committee to adjust the budget to
provide of the original scope of renovation of
the Memorial Hall project instead of cutting
project components.
There have been a number of
changes and adjustments regarding this project
since its inception in 1998 regarding the scope
of work and funding. These have been discussed by
the appropriate committees and reported to the
Council along the way. We are now at the point
where, in the best interest of the City, the
contractor would like to begin his work as soon
as possible. Due to weather concerns, the
contractor would like to start the roof work
before bad weather sets in. In the phasing plan
of the improvements, the roof work was in the
first phase to be completed. After a contract is
signed, the contractor (according to
conversations with him) will need approximately
fourteen days or so, to get this documentation in
place to begin his work. If the contract is
approved at the October 23, 2001, meeting, work
may begin in early to mid-November. If it is not,
the work probably will not be able to begin until
late November."
Tom Short, City Administrator
NASCAR
to the Max
The NASCAR tour makes its
annual trip to the desert southwest and the
1-mile D-Shaped oval in Phoenix, Arizona this
weekend. The drivers find the track very
challenging because there is very little banking
through the turns and all of the turns have a
different radius.
In addition to normal
grandstand seating, Phoenix offers another
option, mountainside! Spectators may purchase
general admission tickets for viewing the race on
a large mountain situated on the outside of turns
three and four. By race time, among the rocks and
cactus, the hillside will be covered with lawn
chairs, blankets, sunshades and a very
enthusiastic crowd. Flat track specialists Dale
Jarrett, Jeff Gordon, and Bobby Labonte will be
among the favorites of the 43 drivers who will
start the race.
Dale Earnhardt, Jr. claimed the
win at last weekends race at Talladega,
Alabama. Talladega was the sight of his late
fathers memorable charge from 18th to 1st in the last
five laps of last years race and also marked the
last win of the elder Earnhardts career.
There were 32 official lead changes, which are
only counted at the start finish line, among 13
drivers during the 188 lap, 500-mile event.
The cars ran three abreast
throughout the race with periods of four and five
abreast as expected. Racing in such tight packs
at Talladega and Daytona leads drivers and fans
alike to expect "The Big One," a
multi-car accident which eliminates significant
numbers of cars from competition. These multi-car
accidents have become common occurrences at these
speedways.
"The Big One", a
sixteen car pileup, occurred on the final lap of
Sundays race and relegated several of the
days frontrunners to finishes in the middle of
the pack. Those who had challenged for the lead
or had led during the day but were involved in
the wreck included Bobby Labonte, Bobby Hamilton,
Sterling Marlin, and Ricky Rudd. Jeff Gordon
added 61 points to his lead over Ricky Rudd and
unless Gordon forgets to show up for any of the
remaining races he will win this years
Winston Cup Championship.
|
Sponsored by
Metcalf Auto Supply
|
Weekly Column
Click &
Clack
TALK CARS
by Tom & Ray Magliozzi
Dear Tom and Ray:
I have an Olds Cutlass Ciera
with 40,000 miles on it, and it has been a great
little car. To make a long story short, I was
having a problem with overheating, and my GM
dealer examined the car and told me I had a
cracked engine block. I had a new short block and
a crankshaft installed, but when I got the car
back, I was still having problems with the
temperature.
After 30 or 40 miles of
driving, the temperature gauge started creeping
up past the halfway point. I took it back and
they replaced a thermostat sensor. I drove it
again, and after 30 miles or so the temperature
started going up again. Now Im afraid to
drive the car any distance. Could it be that the
fan motor isnt kicking on? Gentlemen,
Im 82 years old, and I need wheels because
Im not too good on roller skates. -Hy
RAY: Hi, Hy. Sorry, I
couldnt resist that one. Lets
consider the best and worst-case scenarios first,
since its probably neither of those.
TOM: The best-case scenario is
that everything is fine. You say that the
temperature gauge creeps up past the halfway
mark, but you dont say whether it KEEPS
going. If it stops just above the halfway point
and stays there, that may just be the result of
the new block breaking in and running a little
hotter than normal right now. And that would be
nothing to worry about.
RAY: The worst-case scenario is
that your dealership made a mistake and failed to
notice that the cylinder head, not the block, was
cracked. Or that the head was cracked in addition
to the block.
TOM: But lets not be
alarmists. There are several other good
possibilities here. It could be a faulty fan, as
you suggest, and thats very easy to check.
|